LANG HANCOCK RAIL DRAINAGE REPAIR WORKS
March 2019 - April 2019
Earthworks and drainage works to improve the rail network to Hope Downs 1, approximately 70km West of Newman.
Earthworks and drainage works to improve the rail network to Hope Downs 1, approximately 70km West of Newman.
- Remove 160m of 900mm diameter culverts and replace with 1200mm to 1800mm diameter culverts using cement stabilised fill;
- 750 tonnes of rock armour installed;
- Earthworks to improve drainage;
- Pavement construction;
- Spray seal;
- Non-destructive service locating;
- Rehab.